General Planning

Site relocation Sanomed, Vöhringen



Client
Sanomed Gesundheits- und Sportnahrungsmittelhersteller GmbH


Programming period
2017 - 2020

Scope of service

Sanomed is building its new location on the north-eastern outskirts of Vöhringen. The currently rented company buildings in Neu-Ulm will be abandoned. The building complex will include rooms for production, storage, workshop, research and administration. In intensive planning workshops, a design was developed together with the client that optimally reflects the material flows and work processes of the company. The possibility of a future expansion was also taken into account in the planning. The building project is scheduled for completion by mid-2020, so that the move can be completed by the end of 2020.

  • Object planning building according to HOAI, work phase 1-8
  • Structural design according to HOAI, work phases 1-6
  • Building physics proof of constructive fire protection
  • Engineering inspection
  • Project planning for outdoor facilities according to HOAI, work phase 1-8
  • Project planning of traffic facilities according to HOAI, work phase 1-8
  • Technical equipment according to HOAI, work phase 1-8 (HLS)
  • Technical equipment according to HOAI, work phase 1-8 (ELT)
  • Sound expert opinion
  • Subsoil expertise
  • Fire protection
  • Thermal insulation

 

Your contact person

Stefan Hafner
Teamleader General Planning | Controlling | Finance

stefan.hafner@klingconsult.de